The renovation of the Berlin-Hamburg railway line begins in Havelland. Work from August 1, 2025 to April 30, 2026, replacement traffic set up.

Im Havelland beginnt die Sanierung der Bahnstrecke Berlin-Hamburg. Arbeiten vom 1. August 2025 bis 30. April 2026, Ersatzverkehr eingerichtet.
The renovation of the Berlin-Hamburg railway line begins in Havelland. Work from August 1, 2025 to April 30, 2026, replacement traffic set up.

Mega railway renovation: Berlin-Hamburg completely closed from August 2025!

A major project is just around the corner: the railway line between Hamburg and Berlin is being comprehensively renovated. A general renovation is planned, which will be carried out by...August 1, 2025 to April 30, 2026should last. Deutsche Bahn has already started preparatory work in the last few days, which will have far-reaching effects on many commuters and travelers in the region. In Falkensee, areas east of the train station have already been leveled and paved, where switches and building materials are stored to ensure that construction work runs smoothly.

The entire work not only affects the tracks, but also switches, overhead lines and the renewal of the control and safety technology. Overall will be around28 transport stations along the route were modernized, which promises to significantly improve the travel experience. Environmental and species protection aspects are also taken into account: the previously selected areas will be renatured or returned to their original use after construction work has been completed. [maz-online reports].130 construction site furnishing areas, which are along the278 kilometer long routewere set up.

Impairments and replacement traffic

The route between Hamburg and Berlin will be completely closed for the duration of the renovation. The changes in regional and long-distance transport should therefore not be underestimated. Commuters have to expect significantly longer journey times: the journey from Falkensee to Spandau is extended by more than 20 minutes, which could represent a significant change for many travelers. The travel time between Hamburg and Berlin will also be up toExtend 45 minutes. [Deutsche Bahn informs](https://www.deutschebahn.com/de/presse/presse-regional/pr-berlin-de/aktuell/presseinformationen/Generalsanierung-Hamburg-Berlin-Weiter-direkte-Fernzuege-und-um comprehensives-Ersatzangebot-im-Regionalverkehr-13276614) about the numerous changes to the offer that travelers expect.

A comprehensive replacement offer is being provided for the affected regional transport lines, including lines RE8, RE6, S1 and RB73. Over170 buseson26 lineswill be in use and up to daily86,000 kilometersput back. Passengers can also look forward to a new direct connection RE85 from Schwerin to Berlin every 2 hours.

Travel more modern and attractive

Overall, as part of the renovationmore than 180 kilometers of tracksas well as round200 switchesrenewed, and it will besix additional transfer pointscreated to increase the stability and flexibility of rail traffic. The train stations themselves will also be made more attractive, with new toilet facilities and improvements in accessibility. In order to make planning easier for passengers, the timetable data is now available on bahnbetrieb.de and in the app DB Navigator available.

Another important step is the construction of radio masts for the upcoming FRMCS railway radio, which should further advance the future of rail transport in Germany. Virtual information events are also offered by the DB and VBB to keep the public informed at all times.

The upcoming changes are to be viewed as entirely positive, even if the adjustments to the new circumstances will initially pose some challenges for commuters and travelers.